Our Brief
History:
February 2006
Ground preparation for 50 acres
Purchased Packhouse in Arbroath
March 2006
First students arrive
Planting begins
Packhouse Construction
April May 2006
Poly tunnels construction starts
Pass Assured Produce Audit
Planting 1 Million Plants ends
Packhouse Construction
June 2006
Packhouse Officially Opened
First Fruit Picked on 8th June
Delivery to Asda Dundee
Further 80 Students Arrive
Packhouse Becomes BRC Accredited
July to December 2006
400 tonnes picked packed distributed and SOLD |